+ Reply to Thread
Results 1 to 8 of 8

Thread: Remodel Project

Hybrid View

  1. #1
    Join Date
    Mar 2013
    Posts
    3

    Question Remodel Project

    I need to paint the entire interior of my house. I also need to replace carpet with hardwood floors. Which job should I complete first?

  2. #2
    Join Date
    Mar 2013
    Location
    Raleigh, NC
    Posts
    1

    Default Re: Remodel Project

    Hi there!
    I suggest you paint the walls first, then replace the carpet with hardwood flooring. If you do the flooring first, you will have to be very careful when you are painting (moving the ladder, paint splatters, covering the entire floor, etc).

    It's easier to paint first as the floor is not as big a concern if you do them reversely.

    Hope this helps! Let me know if you have additional questions.
    Doug Muhle
    Raleigh Home Remodeler

  3. #3
    Join Date
    Aug 2007
    Posts
    6,967

    Default Re: Remodel Project

    I second the motion of paint first, flooring last, for the very same reasons.
    I suffer from CDO ... Its like OCD, but in alphabetical order, LIKE IT SHOULD BE!!!

  4. #4
    Join Date
    Sep 2012
    Location
    Boston
    Posts
    1,004

    Default Re: Remodel Project

    Quote Originally Posted by A. Spruce View Post
    I second the motion of paint first, flooring last, for the very same reasons.
    i'll "third" the motion. all you'll have to do is paint or touch up the base trim after the floors are installed.

  5. #5
    Join Date
    Jul 2010
    Location
    SoCal
    Posts
    6,398

    Default Re: Remodel Project

    All of the above are correct. This is elementary.

  6. #6
    Join Date
    Aug 2007
    Location
    Portland, Oregon, formerly of Chicago
    Posts
    1,757

    Default Re: Remodel Project

    I might be the contrarian here.

    If the flooring is to be finished in place hardwood, I always preferred to be there after the finishing. Finishing in place raises sanding dust which tends to stick to everything. The actual staining and varnishing also risks damaging the walls, not to mention accidental scuffing and dings of the walls. Of course, this meant that I had to completely cover the area with rosin paper to protect it from paint splatter, dust, and scratches.
    In later years, I routinely covered hardwoods wall to wall even in existing housing. It just protects the floor and simplifies clean-up at the end of the job.

    If the flooring is pre-finished, I would go along with the others here, although there is plaenty of opportunity to ding up the walls and ceilings while handling all those lengths of flooring.

    When doing new construction, I wanted to be there right before the carpet went down, but after the hard flooring. Of course, drywall primeing, ceilings, etc. might be done as called for during the construction.

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •